Working requirements · 4 October 2026

A home designed around how we actually live.

This evolving brief captures how our family wants the home to work—not just how it should look. Please use it to understand our priorities, test design proposals and identify decisions that need our input.

Working brief — not a construction drawing or final specification.

Design direction

Warm contemporary minimalism

Clean geometry, uncluttered surfaces and restrained detailing, grounded in warm neutrals, natural walnut and controlled black accents.

Warm ivorySandWarm taupeNatural walnutSoft black

Owner-supplied reference images. These communicate mood, materials, lighting and selected design qualities only. They are not approved layouts, products, dimensions or construction details. Original sources were not recorded; embedded credits and watermarks have been preserved.

Explore all inspiration →

Owner requirements aligned

15 of 15 area briefs merged

Design development and selections now underway.

View project status →

Start here

What should guide every proposal

01

SYS-SP-001 — Agreed and reclassified as non-negotiable on 23 August 2026: Fully rewire the home and size the new electrical installation for the confirmed and reasonably foreseeable loads, including the planned AC system and selected water-heating system. A professional inspection may inform implementation details but does not reopen the agreed full-rewiring scope.

Whole-home systems
02

SYS-NN-002 — Provide wired network connections to every room using cabling and network equipment rated for the selected PoE standard. Yasmin deferred network specifics to Fahmi; Fahmi's detailed network positions remain attributed below.

Whole-home systems
03

FOY-NN-002 — Agreed: Provide convenient storage for daily bags, including at least the school bag and handbag. Use a practical combination of quickly accessible open hooks and concealed storage at adult height.

Entrance & foyer
04

FOY-NN-004 — Agreed: Provide a smart lock and a wired or PoE-compatible video doorbell. Coordinate final models, power, cabling, recording and lock arrangement before doors, gates or carpentry are fixed.

Entrance & foyer
05

LIV-NN-001 — Agreed: Remove the existing living-area storeroom to enlarge the common space.

Living area
06

LIV-NN-003 — Agreed: Provide two professionally sized AC blowers across the combined living/dining zone, coordinated for effective airflow, efficient trunking and service access.

Living area
07

DIN-NN-001 — Agreed: Provide space for at least a six-seater rectangular dining table in its normal configuration and make seating eight people comfortable without cramped everyday circulation.

Dining area

Reference drawing

Start with the existing layout

The original HDB floor plan for 893A Tampines Avenue 8. Use it to understand the existing arrangement; dimensions and site conditions must still be verified before design or construction.

Open the complete single-page PDF
Dimensioned floor plan of the executive apartment at 893A Tampines Avenue 8
Existing plan · HDB scale 1:100

The full PDF also includes HDB's notes on structural elements and on-site verification.

Room by room

Explore the requirements

Shared spaces

Entrance & foyer

Create a compact, uncluttered arrival zone that lets the family put down carried items, remove and store shoes, sit, charge small devices and handle parcels without clutter spilling into the Living area. Preserve clear circulation, robot-vacuum access, privacy, security and useful natural airflow.

3 feasibility checks3 decisions/selections
Open brief →

Living area

Create a spacious, flexible and uncluttered family living zone near the entrance. It should support everyday television viewing, reading, conversation and children's floor play, provide comfortable hosting capacity and retain open circulation toward the bedrooms and balcony without recreating the cramped feel of the existing home. Yasmin's preferred adjacency to the study is preserved as an attributed layout position.

4 feasibility checks4 decisions/selections
Open brief →

Dining area

Provide a comfortable, open dining area for the three-person household and for hosting up to eight seated guests without reproducing the cramped feel of the existing home. Coordinate the table, circulation, serving, water-dispenser station, airflow, lighting and adjoining Living, Kitchen and WC2 features as one measured layout.

4 feasibility checks3 decisions/selections
Open brief →

Balcony

Create a calm, welcoming and reconfigurable balcony centred on the existing digital piano, reading and relaxation while retaining capacity for children's play, useful ventilation, weather resilience, easy maintenance and a barrier-free connection to the living and dining area.

5 feasibility checks0 decisions/selections
Open brief →

Corridor windows & privacy

Replace the Study and Living-room windows and grilles facing the common corridor with a coordinated system that prevents passers-by from seeing inside, excludes insects, supports useful natural ventilation, closes fully for air-conditioning and preserves security. Available privacy and window systems must be reviewed before the final daylight and maintenance trade-offs are selected.

5 feasibility checks2 decisions/selections
Open brief →

Private rooms

Main bedroom

Create a calm, uncluttered room for sleep, dressing and prayer. Plan around the existing king-size bed, preserve generous bedside circulation, support a future cot without permanent baby-specific carpentry, and coordinate blackout, acoustics, cooling and condenser maintenance access before fixed works.

3 feasibility checks0 decisions/selections
Open brief →

Bedroom 2 / child's room

Create an appealing, safe bedroom that helps the five-year-old child transition to independent sleep while supporting play, reading, homework and crafts. Use adaptable furniture and service locations so the room can mature through the school years without major renovation.

2 feasibility checks1 decisions/selections
Open brief →

Bedroom 3

Retain a useful, flexible Bedroom 3 while accommodating the relocated Storeroom. Provide a single bed for guest use and a computer/study table while also supporting occasional work, hobbies, family prayer and possible future nursery use. Preserve the jointly allocated wardrobe capacity and practical circulation.

4 feasibility checks2 decisions/selections
Open brief →

Study

Create a separate, comfortable and orderly study for focused work, studying and video calls. Coordinate the repartitioned room with Bedroom 3 and the relocated storeroom, and design primarily for one active user at a time.

5 feasibility checks5 decisions/selections
Open brief →

Storeroom

Create a dry, ventilated, accessible and low-maintenance household store between Bedroom 3 and the study. The layout should prevent overcrowding, support safe retrieval without routine climbing and accommodate the owners' identified bulky items.

5 feasibility checks3 decisions/selections
Open brief →

Meeting agenda

Decisions that still need input

Whole-home systems

SYS-DO-006 — Compare gas instantaneous, electric instantaneous and electric storage water-heating systems against simultaneous bathroom use, kitchen hot water, delivery time, temperature and pressure stability, operating cost, space, utilities and service access.

→
Whole-home systems

SYS-DO-024 — Select the central network-cabinet location, incoming-fibre route, access-point locations, mobile-internet antenna route and UPS scope after verifying the equipment inventory and cable paths.

→
Whole-home systems

SYS-DO-025 — Finalise the complete circuit and load schedule, distribution-board size, dedicated high-load circuits, spare capacity and any space for DIY energy-monitoring CT clamps after the AC and water-heating systems are selected.

→
Whole-home systems

SYS-DO-026 — Finalise the distributed charging-point plan and the location, capacity and form of Fahmi's proposed shared charging station without oversized carpentry or surface clutter.

→
Whole-home systems

SYS-DO-027 — Finalise the whole-home lighting and switching plan by coordinating the requirements already agreed or attributed within each area master.

→
Whole-home systems

SYS-DO-028 — Confirm the owner-selection and equipment schedule, required information, dependencies and decision deadlines before affected design, services, carpentry or procurement are locked in.

→
Entrance & foyer

FOY-DO-006 — Select the new main-door, gate, privacy treatment and digital-lock arrangement. Options recorded by Fahmi include a lock on the main door, on the gate, or synchronised locks on both; Yasmin has deferred product and feature preferences to Fahmi. Confirm compliance and reliable emergency/manual operation.

→
Entrance & foyer

FOY-DO-020 — Confirm the exact distribution-board and fibre-termination locations and decide the whole-home network-cabinet location through the Whole-Home Systems workflow rather than forcing the network equipment into the foyer.

→
Entrance & foyer

FOY-DO-021 — Finalise the visible and concealed socket mix, USB-C or replaceable plug-in charging arrangement and electrical load after the integrated carpentry layout is developed.

→
Living area

LIV-DO-023 — Finalise the television size, wall treatment, viewing distance, furniture orientation, supplementary seating and exact permanent-seat count after reviewing measured layouts.

→
Living area

LIV-DO-024 — Decide the central network-cabinet location and whole-home smart-home standard in the Whole-Home Systems workflow; do not resolve either solely within the Living design.

→
Living area

LIV-DO-025 — Verify the dimensions and status of the recliner, soundbar, subwoofer, Apple TV and other media equipment before fixing outlets, wall mounts or carpentry. Fahmi records the soundbar and subwoofer as existing; Yasmin records the soundbar status as still to confirm.

→
Living area

LIV-DO-026 — Finalise whether the Living and Dining zones should read as one continuous space or have a subtle visual distinction after both layouts are developed.

→
Dining area

DIN-DO-020 — Finalise the combined coffee/water station design, tableware storage and exact coffee-machine position. The Kitchen master currently records the coffee machine in agreed powered concealed storage under KIT-YP-027, while Yasmin's Dining brainstorm places the coffee function at the combined station; resolve this cross-area detail before carpentry and services are fixed.

→
Dining area

DIN-DO-021 — Finalise whether the Living and Dining zones read as fully unified or subtly distinct through the coordinated decision already recorded under LIV-DO-026.

→
Dining area

DIN-DO-022 — Coordinate the Dining feature wall with the agreed seamless flush or hidden WC2 external-passage door under KIT-YP-028 and the WC2 master, without compromising access or making the door visually prominent.

→
Balcony

None currently.

→
Corridor windows & privacy

WIN-DO-019 — Review available market solutions, then select the final combination of glazing, privacy treatment, ventilating sections, insect screens, grilles, locks and restrictors based on physical or visual demonstrations of day-and-night privacy, daylight, airflow, security and maintenance.

→
Corridor windows & privacy

WIN-DO-020 — Confirm whether any outward visibility is retained and, if so, through what adjustable mechanism without weakening privacy.

→
Kitchen

KIT-DO-043 — Verify whether Fahmi's existing regular oven and Yasmin's mini countertop oven describe the same retained appliance; record the model, dimensions, load and operating clearances.

→
Kitchen

KIT-DO-044 — Decide whether to install a dishwasher initially, reserve only space and services, or omit it.

→
Kitchen

KIT-DO-045 — Decide whether to provide the provisional under-sink purifier after assessing value, filter servicing, power and reject-water drainage.

→
Kitchen

KIT-DO-046 — Select the final hood type after the interior designer demonstrates cooking-load capacity, duct feasibility, noise, cleaning and replacement access.

→
Kitchen

KIT-DO-049 — After the full-size mock-up test, record the one final approved countertop height in millimetres above finished floor level. Only the numerical height remains outstanding; the requirement and approval hold-points are agreed.

→
Service balcony

SVC-DO-039 — Select stacked or side-by-side future-dryer provision after the retained washer, raised-platform proposal and circulation clearances are measured together.

→
Service balcony

SVC-DO-044 — Decide whether a compact utility sink adds sufficient value to justify its footprint; Fahmi has kept it under consideration and Yasmin recorded no requirement for one.

→
Service balcony

SVC-DO-045 — Verify the remaining existing equipment inventory and models, particularly the washing machine, dehumidifier, vertical steam iron and baskets, before design freeze. The current robot dock is confirmed as the Dreame L10s Special Edition.

→
WC1 master bath

WC1-DO-014 — Confirm the HIP schedule for Block 893A with HDB.

→
WC1 master bath

WC1-DO-015 — Confirm whether window enlargement is necessary, feasible and approvable after assessing the existing opening and the agreed ceiling-circulation-fan arrangement.

→
WC1 master bath

WC1-DO-016 — Select the water-heater type across WC1, WC2 and the kitchen through SYS-DO-006. Yasmin provisionally prefers gas instantaneous if it proves optimal for the three-person household; do not decide this within WC1 alone.

→
WC1 master bath

WC1-DO-017 — Confirm the AC-condensate receiving-drain location through coordination between the ID, plumber and AC contractor. Fahmi prefers WC1, but the final location remains a cross-area technical decision.

→
WC1 master bath

WC1-DO-038 — Agreed design process: Ask the ID to demonstrate full enclosure, fixed-panel, sliding and other suitable shower-screen arrangements for splash containment, circulation, cleaning and maintenance. Fahmi and Yasmin are jointly open to the alternatives and will select the final arrangement after the demonstration.

→
WC1 master bath

WC1-DO-040 — Agreed selection process: Select the integrated vanity product after the ID demonstrates ceramic and suitable alternatives against the jointly accepted performance criteria and both owners review appearance and physical samples.

→
WC1 master bath

WC1-DO-042 — Finalise the entry door, vanity configuration, palette, tile products, drain type, mirror arrangement, lighting controls and accessory positions after measured and technical demonstrations.

→
WC2 common bath

WC2-DO-027 — Select the whole-home water-heating system through SYS-DO-006 and supply hot water to the WC2 shower and basin as the final system allows.

→
WC2 common bath

WC2-DO-028 — Confirm the final AC-condensate receiving drain and route with WC1, the whole-home AC design, the ID, plumber and AC contractor. Fahmi prefers WC1 and does not want WC2 used unless a technical constraint requires it.

→
WC2 common bath

WC2-DO-031 — Finalise the drain type, minimal splash protection, vanity dimensions, step-stool position, rain-shower inclusion, storage configuration, lighting controls and finish palette after measured and technical demonstrations.

→
Main bedroom

None currently.

→
Bedroom 2 / child's room

BR2-DO-021 — Select the exact Boori children's bed model and size after comparing the available options against mattress life, safe access, floor-play area and the future room layout. The Boori direction is jointly agreed; only the product selection remains outstanding.

→
Bedroom 3

BR3-DO-016 — Select the wardrobe door type and final internal arrangement after reviewing the measured room, bed and desk layout. Yasmin has no preference between sliding and hinged doors; Fahmi asks the interior designer to propose the capacity.

→
Bedroom 3

BR3-DO-017 — Select the exact single-bed dimensions and specification after comparing the agreed room functions, prayer-space requirement, circulation and future nursery flexibility.

→
Study

STD-DO-004 — Decide whether to retain or replace the curved door-frame detail. Fahmi prefers replacement with a conventional doorway suited to sound isolation; Yasmin recorded no position on the curved detail.

→
Study

STD-DO-034 — Interior designer to demonstrate the two-desk arrangement—side by side, back to back or on adjacent walls—and the power, network, lighting, storage and chair clearances in normal measured drawings.

→
Study

STD-DO-035 — If two desks cannot fit without compromising the stated requirements, Fahmi and Yasmin must jointly decide the fallback layout; do not silently omit a workstation.

→
Study

STD-DO-036 — Confirm the monitor and device allocation at the second desk and verify all equipment dimensions and electrical loads before finalising outlets or carpentry.

→
Study

STD-DO-037 — Confirm the treatment and location of the entry focal point, award display, closed storage and common-corridor-window privacy layer.

→
Storeroom

STR-DO-028 — Interior designer to demonstrate a measured layout accommodating the shelving, full-height ladder, folded stroller, luggage and a clear aisle.

→
Storeroom

STR-DO-029 — Interior designer to recommend the door configuration and ventilation method against the requirements above.

→
Storeroom

STR-DO-030 — Confirm whether and where hooks or a rail for tote bags will be included.

→